Good morning,
Please see attached the updated Advance Works Notice for the demolition of Finmere Bridge and the new temporary bridge installation.
Please note there will be work across the following weekends and this will involve a road closure of the A4421 and diversion.
Saturday 19th – Sunday 20th June – preparation work
Friday 9th – Monday 12th July – bridge demolition
Friday 23rd – Monday 26th July – bridge installation
This AWN will also be issued on HS2’s Commonplace for wider distribution.
Kind regards,
Lucy
Lucy Colls
Engagement Manager
Eiffage Kier Ferrovial BAM JV | HS2 Team | 5th Floor, Exchange House, 450 Midsummer Blvd, Milton Keynes, MK9 2EA